METHOD STATEMENT FOR INSTALLATION PUDDLE FLANGE
-
Purpose
The purpose of this method statement is to describe methodology for INSTALLATION OF PUDDLE FLANGE.
-
Scope of Works
This method statement is described the procedure for installation of puddle flange conforms to approved materials and shop drawings.
-
Protection and Safety Equipment
- Safety Helmet, Safety Shoes, Safety Vests
- Welding Gloves, Welding Masks
- Safety Belts, Safety Goggles
- Fire Extinguisher
- Caution Tape
- Traffic Control Cones
PROCEDURE FOR INSTALLATION OF SERVICE
– Installation of all pipe sleeves shall be as per approved
– Ensure all work areas are released by the Contractor, before proceeding with the actual installation works.
– All such works shall require that the levels be re-checked on completion.
– Prior to further installation, all required pipe sleeves passing through concrete/brick walls or slab shall be inspected.
– Service pipeline size shall be smaller than pipe sleeve size.